Lower-Lane Drainage Remediation Begins on Oct. 29, 2025

 

October 28, 2025

Dear all Mayfair Lane residents,

Please be advised that starting tomorrow, Wednesday, Oct. 29, Hertel Plumbing will commence with the lower-lane drainage remediation project. They should be arriving between 7:30-8:00 a.m.

Hertel Plumbing anticipates the entire project should last about 4-5 days, barring any unforeseen issues. They also do not anticipate any disruption to our normal ambling and/or automobile activity.    

Project overview:

  1. Fix overhead leaking PVC drainage pipe at #17

  2. Replace the steel casing pipes/leaders with fernco "Y" couplings, which will create easy access and commonality to the underground branches for regular monitoring and maintenance

  3. Scope and snake/jet clean all 25 leaders/branches

Unforeseen issues that may arise (e.g., a crushed underground branch, etc.) will be handled separately.

If you have any questions, please reach out to Mike C.

Thank you,
Your Mayfair Lane Board

 